TriMark USA's Bryan Musgrove Outlines Equipment Rollout Playbook for Menu Launches

Katarina VukovicNovember 1, 20265 min read4 views

At a glance

  • Bryan Musgrove of TriMark USA says location audits, manufacturer lead times and consolidated packaging can smooth new-menu equipment deployments.
  • TriMark USA's Bryan Musgrove recommends building a location-specific rollout playbook, scheduling equipment production from manufacturer lead times, and repackaging small wares by site. His examples show how electrical capacity, counter space and delivery complexity can affect new menu launches.
A conceptual illustration of a commercial kitchen rollout, with a toaster, stacked pans, serving scoops and consolidated delivery cartons arranged around a modular floor plan.

Bryan Musgrove, divisional senior director on national accounts for TriMark USA, has worked on numerous equipment rollouts tied to new menu items. In a discussion of lessons from those projects, he outlined practices aimed at making deployments across multiple locations more predictable, from assessing each site to aligning equipment production with a launch date.

His first recommendation is to create a rollout playbook for every location. TriMark worked with a brand that needed new toasters to add toasted sandwiches to a breakfast lineup that already included biscuits and wraps. The equipment change was not uniform: some sites were ready to plug in the units, while others needed more support. Musgrove noted that electrical capacity may already be maxed out at some locations. In a small mall or urban site, counter space may also be insufficient for a toaster, which can require adding shelving or another table and can affect workflow. A playbook, he said, can separate plug-and-play locations from those requiring additional work.

Build the schedule around manufacturer lead times

The second practice is to build a schedule driven by the equipment manufacturer's lead time. Musgrove described how production capacity can shape the rollout: a manufacturer may be able to produce 200 units, but the relevant question is how long that will take. At a rate of 10 units a week, he said, the order would take 20 weeks. In another scenario, a manufacturer might have inventory for the first 50 units, then need to order parts from overseas, adding eight weeks before it can complete the rest.

For a menu item tied to a marketing campaign around a specific season or occasion, Musgrove recommends working backward from the desired launch date. That allows the operator to establish a timeline that accounts for manufacturing and delivery rather than assuming the equipment will be available on the campaign date.

Consolidate deliveries by location

The third recommendation concerns packaging and delivery. Rather than shipping smaller wares directly to locations in their original boxes, operators can ask their dealer to consolidate and repackage the items into one package per location. TriMark worked with a brand adding macaroni and cheese to its sides. The change required visual holding cabinets, pans and serving scoops in varying sizes. TriMark combined those items into one package for each location, including instructional materials and exterior labeling so managers knew what they were receiving when the delivery arrived.

Musgrove's advice covers three stages of an equipment rollout: deciding which locations need more support, setting a schedule from manufacturing lead times, and simplifying deliveries. Following those practices, he said, can help ensure a smoother rollout. If the plan proceeds as intended, the new menu item can generate buzz and increase traffic, though the outcome is framed as an expectation, not a verified result.

Reported by Katarina Vukovic, Laser Cutting & Source Specialist.